Last     night Jason whipped up a nice dinner for us.  He just whipped     it up!  Grilled chicken, green beans and little red potatoes     baked golden brown.  Yum!  Jason is always making     delicious meals.  He could be a chef!  He may think it’s a     thankless job, but I am thankful everyday for his cooking.      Thank you Jason!
         Speaking of food, my sister Kristin     has entered into a three way agreement with some friends of hers to     get a fresh bin of fruits and veggies from a local farm each week     starting yesterday.  As soon as she sends me a picture of her     goods I’ll post it!  I was looking into purchasing my own     “share” of a local farm this season…but with just Jason and I, we     were afraid we’d have too much food each week.  We’re hoping     that the petition goes through for a farmer’s market to set up shop     in Cameron Station on Sundays.  No word on whether that’s     happening yet.  
         Not to mention  - no word on the     closing date of our new condo.  We are spinning with     excitement, yet, with no closing date, I feel like we’re hovering in     space….just waiting for that day to be set…so we can plan our move!      Once again, the general move-in time has been extended.  We’re     now looking at mid-August!  Here’s the latest update from     Cameron Station!
         ~~~~~BIG     NEWS!!  The fourth floor units are going into drywall!      This is a critical component for our final permits and one of the     last BIG steps towards completion.
            The lobbies and corridors on the ground, first and second floors are     well on their way with final paint and trim this week.  We have     just (today) received the hydro inspection on the sprinkler system     which will now allow us to close in the remaining portions of the     corridors.  Carpet will be installed in the ground floor     corridors over the next week.  We will be sending pictures of     these areas out in the next new letter.  We hope you are as     impressed as we are with the paint and trim selection.  They     are stunning!
            The exterior grading in hardscape is in the final stages.  The     hardscape at the lobby entries will be completed this week and is     looking great.  The irrigation system for the courtyard and the     fountain has been completed and is being tested on a timing system     and should be up and running soon.
            Internal Quality Inspections are underway on the 2nd     floor.  (That’s us!) The ground and first floors have been     completed and the units are in “lock-down” mode waiting final     cleaning and PSO’s.
            Highlights from the preliminary walk-through with the city will be     shared next week.~~~~~~